06 February 2019

METRO NEWS.

Contd..............
Painting of the structural works is in full swing. This is true particularly for stretch between Subash nagar Metro Station and Breakfast Story restaurant. Two hi-lifts are been working in this stretch.
Painting work in stretch between Breakfast Story and Dada Kripa Glass has not even started. Wonder why the contractor is not being pulled up. See photos.
Similarly work on installation of electrical poles and related electrical infrastructure if almost at stand still after a modest start.
Work on clearing of damaged foot path is progressing. Wish they make foot paths early which will be a boon to morning walkers like me.
Contractor sleeping.

Painting work in full swing. 

Painting work in full swing. 

Painting work in full swing. 

Painting work in full swing. Two High- lifts pressed in service

Painting work in full swing. Two High- lifts pressed in service
Installation of electric poles and related electrical equipment lagging behind badly.

To be contd..........